bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Twinkle

Bashundhara R/A, Dhaka
Expected Completion Date May 2026
Status Updated April, 2026
Back to all projects
Twinkle

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation 100% completed
02 Super Structure work 100%
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A- 4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8=100%, A-9=100%
04 Electrical conducting work 90%
05 Door frame fitting work A-1 =100%, A-2= 100%, A-3= 100%, A- 4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8=100%, A-9=100%
06 Sanitary & plumbing line work N/A
07 In side Plastering work A-2= 100%, A-3= 100%, A- 4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
08 Electrical cable wiring work 100%
09 Wall tiles work 100%
10 Common sanitary & Plumbing line work 90%
11 Outside plastering work 100%
12 Floor tiles/Marble work 100%
13 L.C.C work 100%
14 Grill & Railing work 95%
15 Inside paint & Polishing work 80%
16 Switch -Socket fitting work 80%
17 Outside paint work 70%
18 Door shutter work 90%
19 Aluminum work 90%
20 Tiles Pointing work & Marble finishing work 90%
21 Commode – Basin fitting work and C.P fittings work 90%
22 Lift/Generator /Substation /Solar work 90%
23 Boundary wall /Ground floor development work 90%
24 Roof top finishing work

 

90%
25 Roof top Gardening work G.F Garden work 90%

 