bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Welcome Home

Mirpur, Dhaka
Expected Completion Date November 2026
Status Updated April, 2026
Back to all projects
Welcome Home

Construction progress details

The progress table comes directly from the WordPress post content.

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 95% completed
Block work A Type =100%

B Type =98%

C Type =95%

D Type =100%

E Type =98%

F Type =100%

G Type =100%

H Type =95%

I Type =100%

J Type =95%

K Type =100%

Conduit Pipe Work A Type =100%

B Type =100%

C Type =100%

D Type =100%

E Type =100%

F Type =100%

G Type =100%

H Type =90%

I Type =100%

J Type =100%

K Type =100%

Door frame fitting work A Type =100%

B Type =100%

C Type =95%

D Type =100%

E Type =90%

F Type =100%

G Type =100%

H Type =98%

I Type =98%

J Type =70%

K Type =100%

Sanitary & plumbing line work A Type =90%

B Type =90%

C Type =80%

D Type =90%

E Type =60%

F Type =100%

G Type =100%

H Type =80%

I Type =80%

J Type =50%

K Type =90%

In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

12th Floor Ceiling=95%,

13th Floor Ceiling=95%,

Inside Wall Plaster:

1st floor 90%,

2nd floor 95%

3rd floor 95%

4th floor 95%

5th floor 95%

6th floor 90%

7th floor 90%

8th floor 90%

9th floor 90%

10th floor 90%

11th floor 90%

12th floor 90%

13th floor 90%

 

Electrical cable wiring work Basement= 95%,

Ground Floor=60%

1st floor 10%,

2nd floor 10%

3rd floor 80%

4th floor 80%

5th floor 20%

6th floor 20%

7th floor 20%

8th floor 20%

9th floor 20%

10th floor 20%

11th floor 20%

12th floor 10%

13th floor 10%

 

Wall tiles work Wall tiles work

1st floor 40%,

2nd floor 90%

3rd floor 90%

4th floor 90%

5th floor 90%

6th floor 90%

7th floor 90%

8th floor 90%

9th floor 90%

10th floor 90%

11th floor 90%

12th floor 80%

13th floor 80%

 

Common sanitary & Plumbing line work 1st Floor = 40%,

2nd Floor = 45%

3rd Floor = 45%,

4th Floor = 45%,

5th Floor = 45%,

6th Floor = 45%,

7th floor 30%

8th floor 30%

9th floor 30%

10th floor 30%

11th floor 25%

12th floor 20%

13th floor 20%

 

 

Outside plastering work Outside Wall Plaster:

13th floor 60%

12th floor 70%

11th floor 60%

10th floor 60%

09th floor 60%

08th floor 60%

07th floor 50%

06th floor 50%

05th floor 40%

04th floor 30%

03th floor 30%

02th floor 30%

01th floor 30%

 

Floor tiles/Marble work/Granait work Floor tiles work:

1st floor 7%,

2nd floor 20%

3rd floor 30%

4th floor 30%

5th floor 30%

6th floor 30%

7th floor 30%

8th floor 30%

9th floor 30%

10th floor 30%

11th floor 30%

12th floor 20%

13th floor 20%

 

Granait work:

1st floor 5%,

2nd floor 10%

3rd floor 10%

4th floor 10%

5th floor 10%

6th floor 10%

7th floor 5%

8th floor 5%

9th floor 5%

10th floor 5%

11th floor 5%

12th floor 5%

 

 

L.C.C work N/A
Grill & Railing work 1st floor 0%,

2nd floor 5%

3rd floor 15%

4th floor 15%

5th floor 15%

6th floor 15%

7th floor 15%

8th floor 15%

9th floor 15%

10th floor 15%

11th floor 15%

12th floor 15%

13th floor 5%

 

 

Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 68%

 

Roof top finishing work N/A
Roof top Gardening work N/A