Welcome Home

Mirpur, Dhaka

Completion Date

May 2026

Status Updated

March, 2024

SL. No Name of the work Progress details
  Foundation work 99% Completed
  Super Structure work 47% completed
  Block work A1=95%, A2=90%, A3=90%, A4=80%, B1=95%, B2=90%, B3=80%, B4=80%, C1=92%, C2=90%, C3=90%, C4=80%,  D1=90%, D2=90%, D3=90%, D4=80%, E1=90%, E2=90%, E3=90%, F1=90%, F2=90%, F3=90%, F4=80%,   G1=90%, G2=  90% G3=  80% H1= 90%, H2=90%, H3=90%, H4=50%,  I1=90% I2=90%, I3=80%, I4=50%,   J1= 10%, J2=10%, J3=70%,  K1=90% K2= 90%, K3=90% K4=70%
  Electrical conduit work A1=90%, A2=80%, A3=80%, A4=80%, B1=90%, B2=80%, B3=80%, B4=80%, C1=90%, C2=80%, C3=80%, C4=80%,  D1=90%, D2=90%, D3=80%, D4=80%, E1=90%, E2=90%, E3=80%, F1=90%, F2=90%, F3=80%, F4=80%, G1=90%, G2=  90% G3=  80% H1= 90%, H2=90%, H3=90%, H4=50%,  I1=90% I2=70%, I3=10%, I4=50%, J1= 10%, J2=10%, J3=30%, K1=90%, K2= 80%, K3=70%, K4=70%
  Door frame fitting work N/A
  Sanitary & plumbing line  work N/A
  In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%, 1st Floor Ceiling= 95%,  2nd Floor Ceiling= 95%  3rd Floor Ceiling=95%,  4th Floor Ceiling=90%, 5th Floor Ceiling=25%,

  Electrical cable wiring work Basement= 89%, Ground Floor=60%
  Wall tiles  work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work N/A
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A