Completion Date
May 2026
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
Foundation work | 99% Completed | |
Super Structure work | 47% completed | |
Block work | A1=95%, A2=90%, A3=90%, A4=80%, B1=95%, B2=90%, B3=80%, B4=80%, C1=92%, C2=90%, C3=90%, C4=80%, D1=90%, D2=90%, D3=90%, D4=80%, E1=90%, E2=90%, E3=90%, F1=90%, F2=90%, F3=90%, F4=80%, G1=90%, G2= 90% G3= 80% H1= 90%, H2=90%, H3=90%, H4=50%, I1=90% I2=90%, I3=80%, I4=50%, J1= 10%, J2=10%, J3=70%, K1=90% K2= 90%, K3=90% K4=70% | |
Electrical conduit work | A1=90%, A2=80%, A3=80%, A4=80%, B1=90%, B2=80%, B3=80%, B4=80%, C1=90%, C2=80%, C3=80%, C4=80%, D1=90%, D2=90%, D3=80%, D4=80%, E1=90%, E2=90%, E3=80%, F1=90%, F2=90%, F3=80%, F4=80%, G1=90%, G2= 90% G3= 80% H1= 90%, H2=90%, H3=90%, H4=50%, I1=90% I2=70%, I3=10%, I4=50%, J1= 10%, J2=10%, J3=30%, K1=90%, K2= 80%, K3=70%, K4=70% | |
Door frame fitting work | N/A | |
Sanitary & plumbing line work | N/A | |
In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=90%, 5th Floor Ceiling=25%, |
|
Electrical cable wiring work | Basement= 89%, Ground Floor=60% | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | N/A | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |