Welcome Home

Mirpur, Dhaka

Completion Date

November 2026

Status Updated

September, 2024

Name of the work Progress details
Foundation work 99% Completed
Super Structure work 60% completed
Block work A1=100%, A2=95%, A3=90%, A4=90%, A5=80%,  A6=80%, A7=60%,   B1=95%, B2=95%, B3=90%, B4=90%, B5=80%, B6=70%, B7=50%,   C1=100%, C2=90%, C3=90%, C4=80%, C5=80%, C6=80%,  C7=5%,  D1=90%, D2=90%, D3=90%, D4=90%, D5=90%, D6=60%, D7=5%,   E1=90%, E2=95%, E3=90%, E4=90%, E5=80%, E6=60%, E7=5%,  F1=90%, F2=90%, F3=90%, F4=80%,  F5=90%, F6=80%, F7=5%,   G1=90%, G2= 90% G3=80%,  G6=70%,  H1= 90%, H2=90%, H3=90%, H4=60%, H5=10%,   H6=10%,  I1=95%,  I2=90%, I3=20%, I4=70%, I5=10%, I6=10%, J1= 10%, J2=10%, J3=70%,  K1=95% K2= 90%, K3=90%, K4=70% K5=60%, K6=60%,
Electrical conduit work A1=95%, A2=85%, A3=80%, A4=80%, A5=70%,  B1=95%, B2=80%, B3=80%, B4=80%, B5=80%, C1=95%, C2=80%, C3=80%, C4=80%,  C5=80%, C6=80%,   D1=90%, D2=90%, D3=80%, D4=80%, D5=90%, D6=50%, E1=90%, E2=90%, E3=80%, E4=90%, E5=80%, E6=50%, F1=90%, F2=90%, F3=80%, F4=80%, F5=70%, F6=70%, G1=90%, G2=  90% G3=  80% G6=60%, H1= 90%, H2=90%, H3=90%, H4=50%,  I1=95% I2=70%, I3=60%, I4=50%, J1= 10%, J2=10%, J3=30%, K1=95%, K2= 80%, K3=70%, K4=70% , K5=50%, K6=50%,
Door frame fitting work A1=95%, B1=90%, C1=95%, A2=95%,
Sanitary & plumbing line work N/A
In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%, 1st Floor Ceiling= 95%,  2nd Floor Ceiling= 95%  3rd Floor Ceiling=95%,  4th Floor Ceiling=90%, 5th Floor Ceiling=60%, 6th Floor Ceiling=90%, 7th Floor Ceiling=50%,

Electrical cable wiring work Basement= 90%, Ground Floor=60%
Wall tiles  work N/A
Common sanitary & Plumbing line work N/A
Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work N/A
Roof top finishing work N/A
Roof top Gardening work N/A