Completion Date
May 2025
Status Updated
March, 2024
SL. No | Name of the work | Location | Progress details |
01 | Foundation work | 100% completed | |
02 | Super Structure work | Roof top structure & Parapet wall work ongoing | |
03 | Block Work | Apartment =A1
Apartment =B1 Apartment =A2 Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 Apartment =A12 Apartment =B12 |
75% Completed
90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed |
04 | Electrical conduiting work | Apartment =A1
Apartment =B1 Apartment =A2 Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 Apartment =A12 Apartment =B12 Apartment =A13 Apartment =B13 |
50% Completed
90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 60% Completed 60% Completed 50% Completed 50% Completed |
05 | Door frame fitting work | Apartment =A1
Apartment =B1 Apartment =A2 Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 Apartment =A12 Apartment =B12 |
75% Completed
90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 50% Completed 50% Completed |
06 | Sanitary & plumbing line work | Apartment =A1
Apartment =B1 Apartment =A2 Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 Apartment =A12 Apartment =B12 |
20% Completed
70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 70% Completed 50% Completed 50% Completed |
07 | In side Plastering work | Apartment =A1
Apartment =B1 Apartment =A2 Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 |
60% Completed
75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed 75% Completed |
08 | Electrical cable wiring work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 Apartment =A12 Apartment =B12 |
10% Completed
10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 50% Completed 10% Completed 50% Completed 10% Completed 0% Completed 0% Completed |
09 | Wall tiles work | Apartment =B1
Apartment =A2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11
|
50% Completed
50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 50% Completed 10% Completed 10% Completed 50% Completed 50% Completed 50% Completed 50% Completed
|
10 | Common sanitary & Plumbing line work | ||
11 | Outside plastering work | Apartment =A12
Apartment =B12 |
20% Complete
20% Complete |
12 | Floor tiles/Marble work | ||
13 | L.C.C work | ||
14 | Grill & Railing work | ||
15 | Inside paint & Polishing work | ||
16 | Switch -Socket fitting work | ||
17 | Outside paint work | ||
18 | Door shutter work | ||
19 | Aluminum work | ||
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | ||
22 | Lift/Generator /Substation /Solar work | ||
23 | Boundary wall /Ground floor development work | ||
24 | Roof top finishing work | ||
25 | Roof top Gardening work G.F Garden work |